Your team is developing a new functionality for an employee management system, a Simple Reporting feature. The team is tasked with estimating the test effort required to test this feature.
The team used the standard three-point estimation method to provide the predicted effort.
The team came up with the following estimates:
- in the optimistic scenario, the testing can be done in 1 hour
- in the most likely scenario, the testing can be done in 2 hours
- in the worst-case scenario, the testing can be done in 9 hours
What is the team's final estimation of the test effort?
The team used the standard three-point estimation method to provide the predicted effort.
The team came up with the following estimates:
- in the optimistic scenario, the testing can be done in 1 hour
- in the most likely scenario, the testing can be done in 2 hours
- in the worst-case scenario, the testing can be done in 9 hours
What is the team's final estimation of the test effort?
Suggested Answer: C Vote an answer
Using the three-point estimation formula:
(Optimistic + 4 × Most Likely + Pessimistic) / 6 = (1 + 4×2 + 9) / 6 = (1 + 8 + 9) / 6 = 18 / 6 = 3 hours.
(Optimistic + 4 × Most Likely + Pessimistic) / 6 = (1 + 4×2 + 9) / 6 = (1 + 8 + 9) / 6 = 18 / 6 = 3 hours.
by Jason at Sep 05, 2026, 10:33 AM
0
0
0
10
Comments
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Report Comment
Commenting
You can sign-up / login (it's free).