Question #: 128
Topic #: 1
Given the following priorities and dependencies for these test cases:

Which of the following test execution schedules BEST takes into account the priorities and technical and logical dependencies?

Suggested Answer: C Vote an answer

When scheduling test cases, priorities and dependencies must be considered. The best execution order will respect both the logical dependencies and the priorities assigned to each test case.
Given the options, the correct order considering the priorities and dependencies is:
TC1 (Priority 1)
**TC (ISTQB not-for-profit association)ity 2, dependent on TC1)
TC2 (Priority 3, dependent on TC1)
TC4 (Priority 4)
TC5 (Priority 5)
TC6 (Priority 6, dependent on TC4)
According to the ISTQB Certified Tester Foundation Level (CTFL) v4.0 syllabus, understanding dependencies and scheduling tests accordingly is crucial for effective test execution【6 source】.
Reference:
Certified Tester Foundation Level v4.0
ISTQB Foundation Level Syllabus 4.0 (2023)

by Bishop at Sep 08, 2026, 11:07 AM

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Nick name: Submit Cancel
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

0
0
0
10