All projects use only a single simplified workflow which has three statuses (Open, In Progress, Closed) and all global transitions.
You need to find all issues that were in the Closed status at some point in their lifecycle.
Select the correct JQL query.
You need to find all issues that were in the Closed status at some point in their lifecycle.
Select the correct JQL query.
Correct Answer: B
Vote an answer
It's common practice in your organization to archive projects in the following way:
* The name of archived projects will get the prefix ARCH_
* Archived projects will be assigned the project category ARCHIVE
Recently many projects were archived.
Which JQL query will tell you if there are any unresolved issues in those projects?
* The name of archived projects will get the prefix ARCH_
* Archived projects will be assigned the project category ARCHIVE
Recently many projects were archived.
Which JQL query will tell you if there are any unresolved issues in those projects?
Correct Answer: B
Vote an answer
Explanation: Only visible for EduDump members. You can sign-up / login (it's free).
All projects use a shared permission scheme.
The Browse Projects permission needs to be updated. Project administrators need to be able to manage access to their own projects.
What entry should be added to the Browse Projects permission?
The Browse Projects permission needs to be updated. Project administrators need to be able to manage access to their own projects.
What entry should be added to the Browse Projects permission?
Correct Answer: B
Vote an answer
View the extract of a permission scheme shown below.

Which two statements are correct? (Choose two.)

Which two statements are correct? (Choose two.)
Correct Answer: A,D
Vote an answer
Elaine is the project administrator for the Finance project.
The team requests a brand new field called Currency. It must be added to the screen used on the Approval transition. How can these requirements be met?
The team requests a brand new field called Currency. It must be added to the screen used on the Approval transition. How can these requirements be met?
Correct Answer: A
Vote an answer
Explanation: Only visible for EduDump members. You can sign-up / login (it's free).
A project uses the Simplified Workflow and a Scrum board.
You are the project administrator and the board administrator, but Extended project administration is disabled.
Which two actions can you perform? (Choose two.)
You are the project administrator and the board administrator, but Extended project administration is disabled.
Which two actions can you perform? (Choose two.)
Correct Answer: A,C
Vote an answer
Analyze the workflow scheme for the SSP project shown below:

Which change would require an update to the workflow scheme?

Which change would require an update to the workflow scheme?
Correct Answer: A