A partially created user story for an approval task has been added to the Product Backlog and you have been asked to review it.
So far, the user story includes acceptance criteria stating:
"Verify that the user can select approve or deny."
"Verify that the user can enter an approval comment."
What are two examples of additional content that need to be added to the user story before it can be considered complete?
So far, the user story includes acceptance criteria stating:
"Verify that the user can select approve or deny."
"Verify that the user can enter an approval comment."
What are two examples of additional content that need to be added to the user story before it can be considered complete?
Correct Answer: A,C
Vote an answer
Explanation: Only visible for EduDump members. You can sign-up / login (it's free).
The business has requested a requirement that developers say will be difficult to build in Appian.
Which next step should the Appian Analyst take?
Which next step should the Appian Analyst take?
Correct Answer: A
Vote an answer
Explanation: Only visible for EduDump members. You can sign-up / login (it's free).
Within the "initiate" phase, who is expected to lead and facilitate requirements gathering discussions?
Correct Answer: C
Vote an answer
Explanation: Only visible for EduDump members. You can sign-up / login (it's free).
Which of the following is a key responsibility of a Product Owner in an Agile project?
Correct Answer: B
Vote an answer
Improvements are being considered for an Expense Process, and you have been asked to capture that there is now an approval task sent to the finance manager.
As part of the approval, the process should also reflect that if the payment has not been authorized within 48 hours, a reminder message is sent to the finance manager to inform them they have an outstanding task.
Which Business Process Model and Notation (BPMN) notation type would you use to illustrate the reminder message?
As part of the approval, the process should also reflect that if the payment has not been authorized within 48 hours, a reminder message is sent to the finance manager to inform them they have an outstanding task.
Which Business Process Model and Notation (BPMN) notation type would you use to illustrate the reminder message?
Correct Answer: D
Vote an answer
Explanation: Only visible for EduDump members. You can sign-up / login (it's free).
During the development phase, a feature was identified that was not initially part of the project scope but is now considered crucial.
What should the Appian Analyst do?
What should the Appian Analyst do?
Correct Answer: D
Vote an answer