Identify the missing words in the following sentence.
The [ ? ] should include representation to satisfy the interests of the three primary categories of stakeholders affected by a PRINCE2 project.
Correct Answer: C Vote an answer
Which product summarizes progress and is used to decide whether to amend the project scope or stop the project?
Correct Answer: D Vote an answer
Who represents the three project interests on a project?
Correct Answer: C Vote an answer
Identify the missing words in the following sentence.
When planning the next stage, the Project Manager needs to review and, if necessary, update the [ ? ] with regard to external resources or suppliers.
Correct Answer: B Vote an answer
Which of the following statements about the Closing a Project process are true?
1.The Closing a Project process provides a fixed point for the receipt of completed Work
2.The Closing a Project process provides a fixed point to review if the objectives set out in the original Project Initiation Documentation have been achieved. Packages for the work performed in the final stage.
Correct Answer: D Vote an answer
Which of the following describes a use of a Configuration Item Record?
Correct Answer: B Vote an answer
Which is a purpose of the Directing a Project process?
Correct Answer: D Vote an answer
Which of the following are objectives of the Directing a Project process?
1.Ensure corporate or programme management has an interface to a project
2.Ensure that work on products allocated to a team is authorized
3.Ensure there is authority to initiate a project
4.Ensure that a project remains viable
Correct Answer: B Vote an answer
Which is a purpose of the Closing a Project process?
Correct Answer: A Vote an answer
Which is one of the three levels of plan in PRINCE2?
Correct Answer: A Vote an answer
If a project's benefit tolerance is forecast to be exceeded, to whom should this be escalated to for a decision?
Correct Answer: A Vote an answer
Which product is used by the Project Manager to authorize work?
Correct Answer: C Vote an answer
Which is the Change Authority role permitted to authorize?
Correct Answer: D Vote an answer
Identify the missing words in the following sentence. A Change Authority may be given a [?] to enable it to finance new requirements.
Correct Answer: A Vote an answer