A project aims to deliver a means of enabling the inhabitants of an archipelago to vote via the Internet. Although the technology exists to provide Internet coverage for the islands, it is notoriously difficult (and therefore expensiv(E) to provide robust coverage because of the remote location.
Two of the requirements captured from stakeholders are provided below:
1. The solution shall provide all inhabitants with the ability to
register and vote for a presidential candidate.
2. All voters shall receive an email confirmation that their vote has
been registered within 2 minutes of voting.
Which requirements filter will be particularly relevant in requirements analysis?
Correct Answer: A Vote an answer
An inexperienced business analyst has been asked to conduct scenario analysis. The notes he made about the topic during his training course are rather disorganized, with correct and incorrect assumptions grouped together.
Which of the following notes he made about scenario analysis is incorrect?
Correct Answer: B Vote an answer
Tom is a business analyst working on a project to improve the quality of management information in his organisation. He is developing a new reporting dashboard for senior management and has created a requirements catalogue, partitioned by requirement type. He has also recorded the following 'to do' list of actions:
1) Must record the requirement regarding the system needing to support
up to 25 concurrent users globally.
2) Must record the requirement regarding managers being able to store
and share their comments about the data on the system.
3) Need to record the acceptance criteria for the legal requirements
(this is long overdu(e).
4) Need to check that all standard accessibility requirements are
included.
Which sections of the requirement catalogue will he have updated when he has completed all these actions?
Correct Answer: B Vote an answer
A business analyst working on a project has identified:
* 3 requirements for which there is a workaround and the users can live without;
* 2 requirements that the users can live without for now;
* 15 requirements which, if not delivered, will make the solution
unworkable or useless.
When these requirements are prioritized using MoSCoW, which of the following categories will not be used?
Correct Answer: B Vote an answer
A project manager has stated that he wants 'secure and controlled access to documentation, as well as support for impact analysis and traceability in terms of version history'.
What element of requirements management will offer this?
Correct Answer: C Vote an answer
A business analyst working on a software upgrade project has created a process model, supported by several use case diagrams as part of her requirements work. She is currently compiling the requirements document.
Into which section SHOULD. she put the use case diagrams?
Correct Answer: A Vote an answer
An international travel operator has a customer services department responsible for investigating complaints made by holidaymakers. The department has five members of staff based in its head office.
A business analyst is working on a project to replace the existing holiday management system and has compiled the following requirements from a range of elicitation activities:
1. The solution should be fully accessible in the English, French and
German languages.
2. Users should be able to retrieve holiday details by booking
reference number.
3. Holiday providers shall be able to add the details, date and prices
of their tours directly onto the system.
4. The solution will be able to support up to 2000 concurrent active
users.
5. The solution will be restorable from back-up within 4 hours.
6. The solution should be able to retrieve holiday details within 10
seconds.
Which of the following represents the correct categorization of the requirements?
Correct Answer: B Vote an answer
Below are statements about what a use case model can help the analyst to do:
(A) Establish the scope of a project.
(B) Identify functional requirements.
(C) Understand how data sets are related to each other.
(D) Define the business rules in a process.
(E) Validate how complete a requirements set is.
Which of these statements are true?
Correct Answer: D Vote an answer