BICSI DCDC-002 Actual Free Exam Questions & Community Discussion
what room should the battery room be adjacent to?
Correct Answer: F
Vote an answer
Explanation: Only visible for EduDump members. You can sign-up / login (it's free).
What are the equipment clearance/access requirements when designing the door openings and loading dock areas for a data center?
Correct Answer:
Clearance requirements of 10' L x 4' W x 8' H and 7500 pounds
What is the recommended amount of fuel supply needing to be available to a class F3 data center?
Correct Answer: C
Vote an answer
What is the high temperature that must be maintained in a data center according to TIA-942?
Correct Answer: E
Vote an answer
What is the acceptable rate of temperature change per hour in a data center according to TIA-942?
Correct Answer: E
Vote an answer
What is the difference between a single bus and a dual bus power distribution system?
Correct Answer: D
Vote an answer
What is the acceptable dew point level in a data center according to TIA-942?
Correct Answer: D
Vote an answer
what are the dimensions of circulation pathways?
Correct Answer: C
Vote an answer
Explanation: Only visible for EduDump members. You can sign-up / login (it's free).
How often is there typically a technology refresh in a data center?
Correct Answer: D
Vote an answer
What is the minimum height of a ceiling in a data center or telecommunications room?
Correct Answer: C
Vote an answer
0
0
0
10