Which of the following describe the governance responsibilities of a P3O model?
1.Provides the governance and control backbone for an organization's change initiatives
2.Provides a single source for all data relating to the organization's change initiatives
3.Implements rules for decision-making relating to programmes and projects
4.Makes decisions on behalf of the main board
1.Provides the governance and control backbone for an organization's change initiatives
2.Provides a single source for all data relating to the organization's change initiatives
3.Implements rules for decision-making relating to programmes and projects
4.Makes decisions on behalf of the main board
Correct Answer: C
Vote an answer
Which technique ensures resources with the right expertise are allocated to PPM roles?
Correct Answer: B
Vote an answer
Which of the following statements about how a P3O should integrate with the wider
organization are true?
1.Operates independently of other functions within the organization
2.Typically relies on dedicated full-time resources to provide financial functions needed
organization are true?
1.Operates independently of other functions within the organization
2.Typically relies on dedicated full-time resources to provide financial functions needed
Correct Answer: D
Vote an answer
Which is an activity of the Deliver process within the permanent P3O lifecycle?
Correct Answer: B
Vote an answer
What are risk identification and risk assessment workshops typically used for?
Correct Answer: C
Vote an answer
Why do senior managers need to agree on which PPM problems they rate as critical?
Correct Answer: B
Vote an answer
Which occurs when the P3O implementation programme is closed?
Correct Answer: C
Vote an answer
Which of the following actions are recommended when implementing a P3O model with Hub Portfolio Offices?
1.Appoint a P3O Sponsor to act as Senior Responsible Owner
2.Allow temporary offices to define their own standards and processes
3.Run the implementation as a programme with appropriate governance
4.Use appropriate programme management lifecycles and processes
1.Appoint a P3O Sponsor to act as Senior Responsible Owner
2.Allow temporary offices to define their own standards and processes
3.Run the implementation as a programme with appropriate governance
4.Use appropriate programme management lifecycles and processes
Correct Answer: B
Vote an answer