A customer is buying 10 new Power 720 servers and will integrate them into their existing data center which also has two Power 595s and five Power 750s, taking the total number of systems to
17. All currently installed systems are managed by a single HMC.All the machines will have dual VIO Servers for redundancy, and 10 client LPARs.How can they manage the new machines for the least cost?
Correct Answer: B Vote an answer
Which of the following is a compelling reason to deploy IBM Systems Director Active Energy Manager (AEM) in a data center with high energy utilization?
Correct Answer: D Vote an answer
A new customer wants to install a Power 750 in a warehouse location that has no local staff to support it. They are concerned about hardware support and would like to have the system notify IBM service if there is an issue.Which actions will address the customer concern?
Correct Answer: B Vote an answer
A customer plans to consolidate multiple business unit applications on a single Power Systems server. The maximum number of cores which can be used by each business unit must be limited by creating shared processor pools. What is the minimum PowerVM Edition which provides this feature?
Correct Answer: B Vote an answer
How does the POWER7 processor architecture differ from a POWER6 processor?
Correct Answer: C Vote an answer
Who determines if a Technical and Delivery Assessment (TDA) is required and how in-depth it should be?
Correct Answer: A Vote an answer
A customer is planning to buy a two enclosure Power 770, and will implement 4 LPARs with the following requirements:Each LPAR must have a private, dedicated connection to the network.The adapter for this network connection must be hot-swappable.The customer wants to minimize the number of I/O slots used.Which of the following fulfills the customer requirements?
Correct Answer: B Vote an answer
A Power 720 customer using IVM wants to implement dual VIO servers, but is unable to create the second server. What is the most likely reason for this?
Correct Answer: D Vote an answer
A customer requires their application to have high availability within a data center, and also the ability to recover at a data center located 600km away in the event of an outage. Which system software solution component supports the customer requirement?
Correct Answer: D Vote an answer
A customer has a 4-core POWER6 570 with 4 partitions and a 2-port 1Gbps Integrated Virtual Ethernet (IVE) Adapter. They are having problems with throughput on the Ethernet adapter and want to improve performance. Which of the following solutions will help the customer with this issue for the least cost and with the least interruption?
Correct Answer: C Vote an answer