Microsoft 70-178 Actual Free Exam Questions & Community Discussion
All tasks in your project use the Auto Schedule mode. Several tasks are in progress. You need to reschedule all the remaining work on the project. You also need to achieve this goal without having rigid constraints set to your project's tasks. What should you do?
Correct Answer: B
Vote an answer
Five resources work full time on the project. Standard working hours are eight hours a day from Monday through Friday. John, a team member, asks to take Thursday off from work. He will work on Saturday to adjust this time. You need to ensure that the change in John's working time is reflected in the project schedule. What should you do?
Correct Answer: A
Vote an answer
Your project contains many tasks that have dependencies and result in independent networks of tasks. You need to ensure that you can view critical tasks on all independent networks of tasks within the project. What should you do?
Correct Answer: A
Vote an answer
Your project contains several baselines. By mistake, you save one of your baselines in Baseline5. You need to move Baseline5 to Baseline3 while preserving the baseline information. You also need to create a new Baseline5 by using today's data. Which two actions should you perform? (Each correct answer presents part of the solution. Choose two.)
Correct Answer: A,B
Vote an answer
You need to set the default constraint type for all new tasks to As Late As Possible. What should you do?
Correct Answer: A
Vote an answer
Your project has a part-time resource who works 4 hours a day from Monday through Thursday. You need to ensure that your project plan accommodates the part-time resource. What should you do?
Correct Answer: B
Vote an answer
You need to import a task list from a Microsoft Office SharePoint 2010 site to create a project schedule in Project 2010. You need to achieve this goal while maintaining SharePoint synchronization. What should you do?
Correct Answer: D
Vote an answer