Nokia PDM_2002001060 Actual Free Exam Questions & Community Discussion

  • Exam Code/Number: PDM_2002001060
  • Exam Name/Title: CPM
  • Certification Provider: Nokia
  • Corresponding Certification: Nokia Networks Certification
  • Exam Questions: 215
  • Updated On: Jul 13, 2026
What is the correct approach when handling extra costs of which the customer is deemed
responsible and the relevant purchase order has been received?
Correct Answer: C Vote an answer
When should lessons learned be performed?
Correct Answer: A Vote an answer
What is the primary KPI generated from the Site Quality module of IPM?
Correct Answer: C Vote an answer
Company A is working on a project. The project's budget is EUR10,000. The Planned value as
of date X is EUR4,000. The project is 30% completed. 60% of the budget has been spent. If the company continues to spend money at the same rate, what will the project cost (EAC)?
Correct Answer: B Vote an answer
When should the costs be recognized when utilizing IPM as part of the site process for a customer project?
Correct Answer: A Vote an answer
Continually measuring and monitoring the actual cost versus the budget is done to:
Correct Answer: A Vote an answer
When should a risk be avoided?
Correct Answer: B Vote an answer
In which of the following cases should a project-related cost accrual be booked at period end?
Correct Answer: D Vote an answer
What obligations towards the F&C community does the cost and progress manager have in regards to costs?
Correct Answer: C Vote an answer
Can the project manager start a project when the cost baseline shows an expected -30%
(negative) gross margin?
Correct Answer: A Vote an answer
Company A is working on a project. The project's budget is EUR10,000. The planned value as of date X is EUR4,000. The project has an earned value of EUR3,500 and actual costs of EUR4,500. Which statement is correct?
Correct Answer: B Vote an answer
0
0
0
10