Nokia PDM_2002001060 Actual Free Exam Questions & Community Discussion
What is the correct approach when handling extra costs of which the customer is deemed
responsible and the relevant purchase order has been received?
responsible and the relevant purchase order has been received?
Correct Answer: C
Vote an answer
What is the primary KPI generated from the Site Quality module of IPM?
Correct Answer: C
Vote an answer
Company A is working on a project. The project's budget is EUR10,000. The Planned value as
of date X is EUR4,000. The project is 30% completed. 60% of the budget has been spent. If the company continues to spend money at the same rate, what will the project cost (EAC)?
of date X is EUR4,000. The project is 30% completed. 60% of the budget has been spent. If the company continues to spend money at the same rate, what will the project cost (EAC)?
Correct Answer: B
Vote an answer
When should the costs be recognized when utilizing IPM as part of the site process for a customer project?
Correct Answer: A
Vote an answer
Continually measuring and monitoring the actual cost versus the budget is done to:
Correct Answer: A
Vote an answer
In which of the following cases should a project-related cost accrual be booked at period end?
Correct Answer: D
Vote an answer
What obligations towards the F&C community does the cost and progress manager have in regards to costs?
Correct Answer: C
Vote an answer
Can the project manager start a project when the cost baseline shows an expected -30%
(negative) gross margin?
(negative) gross margin?
Correct Answer: A
Vote an answer
Company A is working on a project. The project's budget is EUR10,000. The planned value as of date X is EUR4,000. The project has an earned value of EUR3,500 and actual costs of EUR4,500. Which statement is correct?
Correct Answer: B
Vote an answer
0
0
0
10
