Your customer is a light assembly manufacturing company that doesn't require shop floor control. A manufacturing engineer wants to generate a work definition automatically for some items, and wants to eliminate the explicit maintenance of work definitions.
Which three steps must be completed and verified in the Work Definition area?
Which three steps must be completed and verified in the Work Definition area?
Correct Answer: C,D,E
Vote an answer
A plant operates three continuous daily shifts of eight hours each for five days in a week. One unit of the resource R1 within the plant is assigned for two shifts to work area W1. On a particular day in a given week, due to unscheduled maintenance that needed to be performed on the resource R1, it was not available for two hours during each of the assigned shifts.
Determine the available capacity of the resource R1 for that week.
Determine the available capacity of the resource R1 for that week.
Correct Answer: B
Vote an answer
A Production operator in your company is required to report production activities, such as completing or scrapping production units, by referencing a work definition without creating work orders.
Identify the manufacturing transaction that a production operator can perform for reporting such activities.
Identify the manufacturing transaction that a production operator can perform for reporting such activities.
Correct Answer: D
Vote an answer
You can generate and manage work order exceptions in Oracle Manufacturing Cloud. Which users can report production exception and who gets notified after an exception is raised?
Correct Answer: D
Vote an answer
The Manufacturing plant has two 8-hour shifts for the work center WC1: Day Shift and Night Shift. You associate four units each for resources R1, R2, R3, and R4 to the work center WC1. The customer wants to assign all units of resource R2 available for Day and Night Shift.
Identify the correct sequence of steps to achieve this requirement.
Identify the correct sequence of steps to achieve this requirement.
Correct Answer: B
Vote an answer
A production operator needs to review the materials issued, resources charged, and operations performed for a job that was executed in the previous shift.
Identify the task the operator has to select to review all the transactions in a single place for both Work Order and Orderless execution.
Identify the task the operator has to select to review all the transactions in a single place for both Work Order and Orderless execution.
Correct Answer: A
Vote an answer
As a production supervisor, you require immediate access to critical shop floor execution systems to take action while on the go.
Which four work order related actions can be taken in the Manufacturing Supervisor mobile application?
Which four work order related actions can be taken in the Manufacturing Supervisor mobile application?
Correct Answer: A,C,D,E