Identify the two capabilities that the Application Development Framework Desktop Integration (ADFDI) framework provides for Work Definitions in Manufacturing Cloud.
Correct Answer: A,C Vote an answer
As a production supervisor, you require immediate access to critical shop floor execution systems to take action while on the go.
Which four work order related actions can be taken in the Manufacturing Supervisor mobile application?
Correct Answer: A,C,D,E Vote an answer
A customer has a distribution warehouse (DW) for After Sales and Service and an in-house manufacturing plant (MP). Sales orders are created and shipped from DW.
Identify the two Sourcing Rules that need to be set for order promising to schedule the order.
Correct Answer: A,B Vote an answer
An order entry specialist creates a Back-to-Back order for product item with an intention of fulfilling by in-house manufacturing. The fulfillment line is scheduled and Supply Chain Orchestration (SCO) has initiated creation of a Supply Order rather than Work Order.
Identify two options that can cause this situation.
Correct Answer: A,B Vote an answer
In a manufacturing plant, two purchase components P1 and P2 and a resource R1 are required to assemble a product. The cost of the assembly is calculated by using the standard costing method. The work definition and resource rates of the assembly have been defined as required.
A cost accountant is estimating cost of the assembly, analyzing rolled-up costs before finally publishing estimates as frozen standards to cost accounting by using a cost planning scenario. While reviewing rolled up costs, the extended costs of purchase components are not included in a rolled-up scenario.
Identify the reason.
Correct Answer: A Vote an answer
Your Customer has implemented Oracle Cloud Manufacturing and the Manufacturing user is in the process of defining Work Definition and Operations. However, this user is unable to assign an ad hoc item, Grease, to an operation.
Identify the reason.
Correct Answer: A Vote an answer
A production Supervisor has noticed that Work Orders created manually are overwritten by the plan runs executed by Planning Central. After discussing this issue with the Planner, two actions are recommended to prevent the Work Orders from being overwritten by plan runs.
Identify the two recommendations.
Correct Answer: B,C Vote an answer