PMI PMI-100 Actual Free Exam Questions & Community Discussion

  • Exam Code/Number: PMI-100
  • Exam Name/Title: Project Management Professional v5
  • Certification Provider: PMI
  • Corresponding Certification: CAPM
  • Exam Questions: 911
  • Updated On: Jun 02, 2026
The following is a network diagram for a project.

What is the critical path for the project?
Correct Answer: D Vote an answer
A reward can only be effective if it is:
Correct Answer: D Vote an answer
Which of the following characteristics are found in a functional organizational structure?
Correct Answer: C Vote an answer
Payback period, return on investment, internal rate of return, discounted cash flow, and net present value are all examples of:
Correct Answer: C Vote an answer
Which Control Scope input is compared to actual results to determine if corrective action is required for the project?
Correct Answer: A Vote an answer
What is the difference between the critical path and the critical chain?
Correct Answer: D Vote an answer
A full-time project manager with low to moderate authority and part-time administrative staff is working in an organizational structure with which type of matrix?
Correct Answer: A Vote an answer
The process of obtaining seller responses, selecting a seller, and awardinga contract is called:
Correct Answer: D Vote an answer
You are assigned to implement the project control plan. What should you do to ensure the plan is effective and current?
Correct Answer: D Vote an answer
Which process in Project Time Management includes reserve analysis as a tool or technique?
Correct Answer: A Vote an answer
Which Plan Schedule Management tool or technique may involve choosing strategic options to estimate and schedule the project?
Correct Answer: C Vote an answer
A special type of bar chart used in sensitivity analysis for comparing the relative importance of the variables is called a:
Correct Answer: B Vote an answer
0
0
0
10