The business analyst is planning an approach to formally manage updates to requirements that may be requested by stakeholders.
What should the business analyst do?
Correct Answer: D Vote an answer
Explanation: Only visible for EduDump members. You can sign-up / login (it's free).
What is a standardized, effective, and efficient way to manage changes to project documentation?
Correct Answer: D Vote an answer
Explanation: Only visible for EduDump members. You can sign-up / login (it's free).
A startup company sells organic vegetable and fruit smoothies. Management is tracking a rapid decrease in sales of their best-selling juice, so they contract a business analyst to identify solutions in order to increase sales by comparing similar products offered by competitors.
Which technique or tool should be used?
Correct Answer: A Vote an answer
Explanation: Only visible for EduDump members. You can sign-up / login (it's free).
A business analyst is trying to determine which analysis technique will be best suited to elicit information from a large number of users in a short period of time. Which elicitation technique is best suited for this purpose?
Correct Answer: C Vote an answer
Explanation: Only visible for EduDump members. You can sign-up / login (it's free).
A new product was designed and delivered to the customer. The product exceeded customer expectations but did not meet the baseline budget for the product. What could be the issue?
Correct Answer: A Vote an answer
Explanation: Only visible for EduDump members. You can sign-up / login (it's free).
Company A would like to enter into a new market. The business analyst has been assigned to a project for which nobody in Company A has any prior experience. The project manager has asked the business analyst to assist in resource planning.
What should the business analyst recommend to the project manager?
Correct Answer: B Vote an answer
Explanation: Only visible for EduDump members. You can sign-up / login (it's free).
One of the main purposes for creating a requirements traceability matrix is to:
Correct Answer: C Vote an answer
Explanation: Only visible for EduDump members. You can sign-up / login (it's free).
During a requirements workshop, sponsors and managers from different departments express varying points of view and priorities about the product's functions and requirements. The business analyst struggles with facilitating the group to reach an agreement.
What should the business analyst have defined to avoid this?
Correct Answer: C Vote an answer
Explanation: Only visible for EduDump members. You can sign-up / login (it's free).
A business analyst is working on a project to update the user interface for a legacy procurement system. An end user raises concerns that the new solution will not support their core business processes.
How could the business analyst address the end user's concerns about the new interface?
Correct Answer: C Vote an answer
Explanation: Only visible for EduDump members. You can sign-up / login (it's free).
The following requirement was included in a business requirements document: "An API shall be built to send data back and forth from the accounting system to the customer relationship system so that name and address data can be synchronized." What should be done with this business requirement?
Correct Answer: B Vote an answer
Explanation: Only visible for EduDump members. You can sign-up / login (it's free).
A business analyst for Company A has been assigned to a three-year project to assist health insurance Company B with implementing and testing a new set of medical codes. The business analyst has identified many stakeholders who will participate in the project. For example, Company A will designate technical staff to write and code the requirements and provide a testing team to test the new functionality. The senior director of Company B will require weekly progress updates. The project manager from Company A will create project plans, schedule meetings, and provide meeting minutes.
In the scenario above, what is the role of the technical staff and testing team from Company A?
Correct Answer: A Vote an answer
Explanation: Only visible for EduDump members. You can sign-up / login (it's free).
A business analyst is developing a traceability matrix to determine whether or not any gaps exist and to identify any discrepancies.

Which critical field is needed to ensure that the traceability matrix is usable?
Correct Answer: B Vote an answer
Explanation: Only visible for EduDump members. You can sign-up / login (it's free).
Which of the following would be the best practice in product validation?
Correct Answer: C Vote an answer
Explanation: Only visible for EduDump members. You can sign-up / login (it's free).