Peoplecert MSP-Practitioner Actual Free Exam Questions & Community Discussion
The Training Project has included some interactive games in the training materials. This is to help engineering staff members share ideas and experiences during the training of how to apply the new processes. However, the CEngO thinks that the engineering staff members will find this approach rather childish as they are very experienced and normally work independently. As a result, the CEngO has asked for the games to be removed from the training materials.
Is the CEngO's request an appropriate application of the 'knowledge' theme, and why?
Is the CEngO's request an appropriate application of the 'knowledge' theme, and why?
Correct Answer: D
Vote an answer
Explanation: Only visible for EduDump members. You can sign-up / login (it's free).
Here are three statements about the programme justification for the Smart Meter Programme. In which document should the statements be recorded?


Correct Answer:

Explanation:
Statement
Document
It is assumed that the Utility Oversight regulator will not introduce a policy that caps prices to reduce the overall profitability of the programme Business case For each option considered, an estimate of the initial cost of operation was calculated Programme brief
10-15% increase in gas and electricity customers; assuming that market research analysis is indicative of future performance Financial plan Strategic assumptions that underpin the financial viability of the investment belong in the Business Case.
High-level options analysis and initial costings are features of the Programme Brief developed during
'Identify the Programme'. Specific growth targets and their financial impact are managed within the Financial Plan
The programme is in the 'plan progressive delivery' process for the first time and the business case has been confirmed. The programme manager is now attempting to get commitment from the Call Centre Manager that they will provide the staff needed in Tranche 1.
Is this an appropriate application of the 'plan progressive delivery' process, and why?
Is this an appropriate application of the 'plan progressive delivery' process, and why?
Correct Answer: D
Vote an answer
Explanation: Only visible for EduDump members. You can sign-up / login (it's free).
The programme is in the first tranche. The programme manager met with the project managers from the Employment Contracts and Call Centre Rationalization projects as well as the BCM. Many topics were discussed. After the meeting, the programme manager reviewed the information gathered at the meeting.
Which information should result in an addition to the risk register?
Which information should result in an addition to the risk register?
Correct Answer: B
Vote an answer
Explanation: Only visible for EduDump members. You can sign-up / login (it's free).
Which of the following is Not one of MSP defined levels of stakeholder engagement?
Correct Answer: D
Vote an answer
Explanation: Only visible for EduDump members. You can sign-up / login (it's free).
The project team working on the Training Project in Tranche 3 needs to understand the new processes and knowledge required by staff members to develop a coherent set of training materials. The project team also needs to know the skills and qualifications for each role, and any new processes. The project manager is concerned that some of the documentation provided is outdated and does not now reflect the current processes being developed.
Which aspect of information management, if applied correctly, is MOST LIKELY to address these concerns?
Which aspect of information management, if applied correctly, is MOST LIKELY to address these concerns?
Correct Answer: C
Vote an answer
Explanation: Only visible for EduDump members. You can sign-up / login (it's free).
Which of the following is an influencer type of stakeholder?
Correct Answer: A
Vote an answer
Explanation: Only visible for EduDump members. You can sign-up / login (it's free).
0
0
0
10