Which of the following take place before the initiation of a project?
1. Appoint the Executive
2. Capture requirements
3. Develop the Project Brief
4. Develop the detailed Business Case
Correct Answer: C Vote an answer
What process provides the information required to decide whether to authorize the delivery of a project?
Correct Answer: D Vote an answer
Identify the missing word in the following sentence. The [?] theme defines that the Project Board is responsible for the overall direction and management of the project,
Correct Answer: C Vote an answer
Which is a purpose of a Project Brief?
Correct Answer: B Vote an answer
What theme establishes the mechanisms to judge whether a project is worthwhile investing in?
Correct Answer: A Vote an answer
Which of the following are typical core activities within configuration management?
1. Planning
2. Risk assessment
3. Verification and audit
4. Identification
Correct Answer: A Vote an answer
Which is a typical core activity within configuration management?
Correct Answer: D Vote an answer
What is the first task of product-based planning?
Correct Answer: D Vote an answer
Identify the missing words in the following sentence.
The [ ? ] should include representation to satisfy the interests of the three primary categories of stakeholders affected by a PRINCE2 project.
Correct Answer: C Vote an answer
Which is a purpose of the Plans theme?
Correct Answer: B Vote an answer
Which process covers the work done by external suppliers who may NOT be using PRINCE2?
Correct Answer: A Vote an answer
Identify the missing words in the following sentence.
A problem/concern, a request for change and [ ? ] are the three types of issue.
Correct Answer: A Vote an answer
Which is a purpose of the Initiating a Project process?
Correct Answer: C Vote an answer
Which is a typical core activity within configuration management?
Correct Answer: D Vote an answer
Which is a true statement about management stages and technical stages?
Correct Answer: C Vote an answer