Exam ISO-31000-Lead-Risk-Manager Topic 1 Question 42 Discussion

Actual exam question for PECB's ISO-31000-Lead-Risk-Manager exam
Question #: 42
Topic #: 1
Scenario 2:
Bambino is a furniture manufacturer headquartered in Florence, Italy, specializing in daycare furniture, including tables, chairs, children's beds, shelves, mats, changing stations, and indoor playhouses. After experiencing a major supply chain disruption that caused delays and revealed vulnerabilities in its operations, Bambino decided to implement a risk management framework and process based on ISO 31000 guidelines to systematically identify, assess, and manage risks.
As the first step in this process, top management appointed Luca, the operations manager of Bambino, to facilitate the adoption and integration of the framework into the company's operations, ensuring that risk awareness, communication, and structured practices became part of everyday decision-making.
After Luca took on the responsibility, he reviewed how responsibilities and decision-making were distributed across the company's units, with each unit overseen by a director managing strategic, administrative, and operational matters. At the same time, in consultation with top management, he analyzed the broader environment of Bambino, namely mission, governance, culture, resources, information flows, and stakeholder relationships.
Building on this, Luca outlined concrete actions to strengthen risk management by engaging stakeholders, breaking the process into stages, and aligning objectives with the company's goals. Progress was tracked through existing systems, allowing timely adjustments. Additionally, clear objectives were linked to the mission and strategy, responsibilities were defined, leadership demonstrated commitment, and expectations for daily integration were clarified. Finally, resources for people, skills, and technology were allocated, supported by communication, reporting, and escalation mechanisms.
Additionally, Luca reviewed the requirements the company was bound by, including safety laws for children's products, local labor regulations, and permits needed for operations. He also considered voluntary commitments, such as sustainability labels and agreements with daycare institutions. Through this review, he identified the likelihood of occurrence and potential consequences of failing to meet these requirements, ranging from legal penalties to loss of customer trust, making this area a clear source of exposure. This included the possibility of fines for breaching product safety laws, sanctions for violating labor regulations, and reputational harm if sustainability or contractual commitments were not fulfilled.
Based on the scenario above, answer the following question:
According to Scenario 2, Luca outlined a concrete set of actions to strengthen the company's risk management capabilities. What did he develop in this case?

Suggested Answer: B Vote an answer

The correct answer is B. Risk management plan. ISO 31000:2018 explains that once leadership commitment and context are established, organizations must design and implement the risk management framework through structured and coordinated actions. A risk management plan translates strategic intent into practical, actionable steps that enable the integration of risk management into everyday operations.
In the scenario, Luca outlined concrete actions such as stakeholder engagement, breaking the process into stages, aligning objectives with organizational goals, tracking progress through existing systems, defining responsibilities, allocating resources, and establishing communication, reporting, and escalation mechanisms. These elements collectively describe a risk management plan, which specifies how risk management will be implemented, monitored, and improved across the organization.
A risk management policy is typically a high-level statement expressing top management's commitment, principles, and overall direction regarding risk management. While leadership demonstrated commitment in the scenario, Luca's activities went beyond policy formulation and focused on execution.
A risk treatment plan is developed later in the risk management process and focuses specifically on actions to modify individual risks. In Scenario 2, Luca's work addressed the framework and integration level, not the treatment of specific risks. A risk register, likewise, is a recording tool and not a set of actions.
From a PECB ISO 31000 Lead Risk Manager perspective, developing a risk management plan is a critical step in ensuring that risk management is integrated, structured, and sustainable. Therefore, the correct answer is risk management plan.

by Christopher at Oct 02, 2026, 01:31 PM

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Nick name: Submit Cancel
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

0
0
0
10