API API-1169 Actual Free Exam Questions & Community Discussion

  • Exam Code/Number: API-1169
  • Exam Name/Title: Pipeline Construction Inspector Exam
  • Certification Provider: API
  • Corresponding Certification: API Certification
  • Exam Questions: 453
  • Updated On: Aug 02, 2026
Permanent trench breakers cannot be installed within a ______________
Correct Answer: D Vote an answer
4 instruments used to inspect field bends
Correct Answer: D Vote an answer
What section covers repairs of dents
Correct Answer: D Vote an answer
What is the typical distance between new and existing pipe?
-1 to 18 in
-12 to 18 in
-12 to 24 in
49 CFR 192.325 and 192.250
Correct Answer: B Vote an answer
Inspect bends for
Correct Answer: D Vote an answer
In the CGA Best Practice, an icon of a green square identifies
-On call center
-Facility Owner
-Designer
-Excavator
Correct Answer: B Vote an answer
If an underground pit is vented, there must be a means of preventing __________ from reaching the vault atmosphere.
Standard?
Correct Answer: A Vote an answer
Verifying that _________ activities are properly monitored and do not result in the ___________ of sand, silt, and/or sediment into sensitive environmental resource areas,
Correct Answer: B Vote an answer
The company installing a utility will ID areas within _______ ft of existing facilities where blasting will take place
Correct Answer: A Vote an answer
Sub-part G 192.309 specifies which dents on pipe must be repaired if the steel pipe is to be operated at pressure that produces a hoop stress of 20 percent or more of SMYS
-Dents more than _____ inches of pipe diameter in pipe over 12 3/4 inches in diameter
-Dents more than ______ inches of pipe pipe diameter in pipe less than 12 3/4 inches in diameter
Correct Answer: A Vote an answer
Define NPDES
Correct Answer: A Vote an answer
Slope (%) Spacing (feet)
5 - 15 ?
>15 - 30 ?
>30 ?
Correct Answer: D Vote an answer
0
0
0
10