You are a project manager who uses Project Professional 2013.
Your organization has been working with a new status report model for the last month. This new status report is created through the Built-in Dashboards and Reports in Project Professional 2013.
The standard Project Professional 2013 report views named Late Tasks and Milestone Report already have all the information required for the new model.
You are assigned to consolidate the information from these two reports into a dashboard view named Status Report Model. Your organization wants to keep the same format, colors, and layout.
You need to implement this solution.
What should you do?
Correct Answer: B Vote an answer
You are an independent project manager who uses Project Professional 2013.
You work on multiple projects for different customers and use only one project to manage their tasks. You invoice your customers on a monthly basis. To identify tasks that have not been invoiced, you create a custom field called Not Invoiced.
Without losing the original project tasks' sort order, and without hiding any information, you need to see all tasks which have not been invoiced.
You create a custom filter based on the Not Invoiced custom field.
What should you do next?
Correct Answer: A Vote an answer
DRAG DROP
You are a senior project manager in a software development company. You manage your projects with Project Professional 2013.
The development team is behind schedule due to a problem found in the architectural design of the database. The lead architect estimates that redesigning the database will take approximately 30 hours. You create a new manual task and assign it to the lead architect. However, the task has not been scheduled.
You need to easily see a time phased view of all tasks for the lead architect in order to schedule the task for completion.
Which three actions should you perform in sequence? (To answer, move the appropriate three actions from the list of actions to the answer area and arrange them in the correct order.)
Correct Answer:

Explanation:
Box 1: Go tothe Team Planner and locate the Lead Architect resource.
Box 2: Select the unscheduled Database Redesign task.
Box 3: Drag the Database Redesign task to the date grid to schedule the work.
Note:
* The Team Planner is a new view in Project 2010 that shows a Gantt Chart-like view of assignments per resource.
You are a project manager for a company that uses Project Professional 2013.
You are responsible for communicating the progress of your projects every month. Your company provides you with a Gantt Chart view that uses the standard Entry table.
You need to communicate the progress of tasks that have a finish date of either October 2 or October 22.
What should you do?
Correct Answer: C Vote an answer
DRAG DROP
You are using Microsoft PPM.
Your organization provides temporary staff to its customers. Temporary staff members are organized into junior level, standard level, and senior level. Each level is further categorized by two rates. The regular rate is for work within 100 kilometers and a higher rate is for work beyond that distance. You must include all temporary staff and all rates in your schedule.
You need to ensure that Project calculates total resource cost immediately when making a resource assignment. You want the ability to switch between the regular rate and the higher rate for each task.
Which four actions should you perform in sequence? To answer, move the appropriate actions from the list of actions to the answer area and arrange them in the correct order.
Correct Answer:

Explanation:

References: https://support.office.com/en-us/article/Add-resources-to-your-project-
1 a744960-d960-426a-b687-e42ba3f6c0cb
https://support.office.com/en-us/article/Enter-costs-for-resources-b4ced847-2655-4fa4- a621-3fc26fc81c88
https://support.office.com/en-us/article/View-project-cost-totals-0d3a2451-fb1e-4ba0-826e-
20ee3b3d60cc
While creating a schedule with Project Professional 2013, you notice that there is a three- day duration on the Database Design task.
After working for only two days, the resource performing the task reports two days of work and notifies you that the task is finished.
You need to update the schedule with this information.
What should you do?
Correct Answer: D Vote an answer
You update a schedule that you are managing by using Microsoft Project.
After the update, you observe that many of the resources in the schedule are overallocated.
You need to resource level the schedule without changing the current projected finish data for the project.
Which three actions will achieve the goal? Each correct answer presents part of the solution.
Correct Answer: A,B,C Vote an answer