Your project managers manage several projects using Project Professional 2013. Each individual project contains a saved baseline.
You need to capture in the master project the baseline data from the member projects at the summary levels for reporting purposes.
What should you do?
You need to capture in the master project the baseline data from the member projects at the summary levels for reporting purposes.
What should you do?
Correct Answer: A
Vote an answer
You are a project manager who uses Project Standard 2013.
Your manager wants you to plan an office move. You have a project schedule from a prior office move named "OfficeMove.mpp" and you want to use this project to assist in planning the current office move.
In the fewest steps possible, you need to create your new project schedule based on the old project schedule.
What should you do?
Your manager wants you to plan an office move. You have a project schedule from a prior office move named "OfficeMove.mpp" and you want to use this project to assist in planning the current office move.
In the fewest steps possible, you need to create your new project schedule based on the old project schedule.
What should you do?
Correct Answer: D
Vote an answer
You are a project manager for a large telecommunications company that uses Project Professional 2013.
The project you have been assigned has a fixed cost of 5150,000. The fixed cost is for the entire project and not for an individual task.
You need to add the fixed cost of S 150,000 to your schedule and spread it across the duration of the project.
What should you do?
The project you have been assigned has a fixed cost of 5150,000. The fixed cost is for the entire project and not for an individual task.
You need to add the fixed cost of S 150,000 to your schedule and spread it across the duration of the project.
What should you do?
Correct Answer: D
Vote an answer
You are a project manager who uses Project Professional 2013.
You are planning an office move, which will occur over a weekend. You use Auto Scheduled tasks and create a weekend working calendar.
You need to assign the weekend working calendar to the task.
What should you do?
You are planning an office move, which will occur over a weekend. You use Auto Scheduled tasks and create a weekend working calendar.
You need to assign the weekend working calendar to the task.
What should you do?
Correct Answer: D
Vote an answer
Your organization uses Project Professional 2013.
A senior stakeholder informs you that your project start date is delayed and gives you a new start date.
You need to change the project start date without adding constraints.
What are three possible ways to achieve this goal? (Each correct answer presents a complete solution. Choose three.)
A senior stakeholder informs you that your project start date is delayed and gives you a new start date.
You need to change the project start date without adding constraints.
What are three possible ways to achieve this goal? (Each correct answer presents a complete solution. Choose three.)
Correct Answer: A,C,D
Vote an answer
You are a project manager who uses Project Standard 2013.
You manage a software development project and have acquired two additional resources to assist in the completion of tasks that are on the critical path. Both resources are also assigned to participate in other projects. Resource1 is available 50% and Resource2 is available 75%.
You need to add the resources with their availability to the project schedule and make any allocation problems visible.
What should you do?
You manage a software development project and have acquired two additional resources to assist in the completion of tasks that are on the critical path. Both resources are also assigned to participate in other projects. Resource1 is available 50% and Resource2 is available 75%.
You need to add the resources with their availability to the project schedule and make any allocation problems visible.
What should you do?
Correct Answer: A
Vote an answer
You manage a project for an organization that uses Project Professional 2013.
You reset the baseline for some selected tasks. After the baseline has been updated with the new values, you realize that some of the summary baseline duration values are not correct.
You need to resolve this problem.
What should you do?
You reset the baseline for some selected tasks. After the baseline has been updated with the new values, you realize that some of the summary baseline duration values are not correct.
You need to resolve this problem.
What should you do?
Correct Answer: A
Vote an answer