NCMA CPCM Actual Free Exam Questions & Community Discussion
Scenario 4.0: 2 - "The Requirements of a Requirements Contract"
In 2019, the buyer awarded National Concrete Supply (NCS) the first of three consecutive contracts for concrete placement, asphalt surface treatments, and pavement markings at one of its facilities. The first one- year contract had an option to extend performance through April 30, 2022. The 2020 contract was a
"requirements type contract to be ordered on individual delivery orders." The scope of the contract required NCS to furnish all labor, materials, equipment, transportation, traffic control, and supervision for construction and repair services. The contract provided that services for concrete work would "include, but not be limited to" base course restoration, crack repair, joint repair, concrete headwalls, complete restoration, concrete curb and gutter, concrete porches, steps, and patios, slab jacking, concrete sidewalks, rapid-set concrete repair, culverts and drainage structures, repair or construction of roads, airfield surfaces, walkways, retaining walls, parking lots, and concrete footings.
The buyer reserved the right "to have work falling within the scope of the contract performed by in-house personnel, job order contracting, or by another contract where concrete placement, asphalt surface treatment, or pavement marking is incidental to other work." The 2020 contract also included clauses stating, among other things, that this was a requirements contract and that the estimated quantities were not the buyer's total requirements, but only estimates of requirements exceeding quantities the buyer might furnish within its own capabilities.

Following expiration of the 2020 contract, the buyer entered into additional one-year contracts in 2022 and
2023. Based on the comparison table provided, the key changes were:
* 2022: Added revisions to site work associated with the placement of concrete or asphalt; added a definition of "incident" as work in, on, and up to a perimeter of 5 feet around the structure or item to complete work if its origin is within that 5-foot perimeter; no change to contract description; no change to the clause stating the contract was a requirements-type contract.
* 2023: Added items NCS would furnish, including engineering/layout, preparing subgrade to receive compacted crushed stone base, and clear and grubbing; deleted the line reserving the buyer's right to have certain work performed by in-house personnel, job order contracting, or another contract where concrete placement, asphalt surface treatment, or pavement marking was incidental to other work; updated the contract description to state the contract was a "requirements type contract for construction
/repair of asphalt pavement, concrete pavement, pavement markings, and site preparation"; and replaced the clause with one stating that the estimated quantities set forth in the 2023 contract, and the buyer's obligation to order under the 2023 contract, excluded work that the buyer itself would perform.
NCS claimed that during performance of the 2020, 2022, and 2023 contracts, the buyer diverted substantial portions of work within the scope sections to other contractors and claimed lost profits under each contract.
Question:
When interpreting the contract, which of the following guidelines for contract interpretation should the court have relied on?
In 2019, the buyer awarded National Concrete Supply (NCS) the first of three consecutive contracts for concrete placement, asphalt surface treatments, and pavement markings at one of its facilities. The first one- year contract had an option to extend performance through April 30, 2022. The 2020 contract was a
"requirements type contract to be ordered on individual delivery orders." The scope of the contract required NCS to furnish all labor, materials, equipment, transportation, traffic control, and supervision for construction and repair services. The contract provided that services for concrete work would "include, but not be limited to" base course restoration, crack repair, joint repair, concrete headwalls, complete restoration, concrete curb and gutter, concrete porches, steps, and patios, slab jacking, concrete sidewalks, rapid-set concrete repair, culverts and drainage structures, repair or construction of roads, airfield surfaces, walkways, retaining walls, parking lots, and concrete footings.
The buyer reserved the right "to have work falling within the scope of the contract performed by in-house personnel, job order contracting, or by another contract where concrete placement, asphalt surface treatment, or pavement marking is incidental to other work." The 2020 contract also included clauses stating, among other things, that this was a requirements contract and that the estimated quantities were not the buyer's total requirements, but only estimates of requirements exceeding quantities the buyer might furnish within its own capabilities.

Following expiration of the 2020 contract, the buyer entered into additional one-year contracts in 2022 and
2023. Based on the comparison table provided, the key changes were:
* 2022: Added revisions to site work associated with the placement of concrete or asphalt; added a definition of "incident" as work in, on, and up to a perimeter of 5 feet around the structure or item to complete work if its origin is within that 5-foot perimeter; no change to contract description; no change to the clause stating the contract was a requirements-type contract.
* 2023: Added items NCS would furnish, including engineering/layout, preparing subgrade to receive compacted crushed stone base, and clear and grubbing; deleted the line reserving the buyer's right to have certain work performed by in-house personnel, job order contracting, or another contract where concrete placement, asphalt surface treatment, or pavement marking was incidental to other work; updated the contract description to state the contract was a "requirements type contract for construction
/repair of asphalt pavement, concrete pavement, pavement markings, and site preparation"; and replaced the clause with one stating that the estimated quantities set forth in the 2023 contract, and the buyer's obligation to order under the 2023 contract, excluded work that the buyer itself would perform.
NCS claimed that during performance of the 2020, 2022, and 2023 contracts, the buyer diverted substantial portions of work within the scope sections to other contractors and claimed lost profits under each contract.
Question:
When interpreting the contract, which of the following guidelines for contract interpretation should the court have relied on?
Correct Answer: D
Vote an answer
Explanation: Only visible for EduDump members. You can sign-up / login (it's free).
__________ are the phases of the contract life cycle.
Correct Answer: C
Vote an answer
Explanation: Only visible for EduDump members. You can sign-up / login (it's free).
Scenario 6.0: 2
ABC Corporation (ABC) entered into a firm-fixed-price, indefinite-delivery/indefinite-quantity (IDIQ) contract with a Federal buyer for the purchase of various "Soviet-style" parts. The contract language allowed for changes to:
o Drawings, designs, or specifications when the supplies to be furnished are to be specially manufactured for the buyer; o The method of shipment or packing; and o Place of delivery.
The contract also specified that:
If any such change causes an increase or decrease in the cost of, or the time required for, performance of any part of the work under this contract, whether or not changed by the order, the buyer shall make an equitable adjustment in the contract price, the delivery schedule, or both, and shall modify the contract.
ABC was unable to obtain a particular part required to fulfill a delivery order under the contract, and missed the deadline for delivery. Two years after the deadline passed, with no delivery, the failure provided cause for termination for default under the conditions outlined in the contract. To avoid default, ABC entered into Bilateral Modification 4 with the buyer. The modification required ABC to provide additional parts as consideration for late delivery. The modification also stated that a new delivery date for the original delivery would be determined in another modification.
ABC remained unable to purchase the parts to fulfill the original order. A new modification, Bilateral Modification 7 , provided that ABC would deliver "new production" models of the parts in question, rather than the "new surplus" parts specified in the original delivery order. The idea to deliver new production models of the parts had originated with ABC and was accepted by the buyer. ABC did not attempt to negotiate any changes in price, no discussions of price were held, and no price adjustment was included in this modification.
ABC completed delivery of these parts on time. However, the new production models cost significantly more than the new surplus parts originally ordered.
Approximately four months later, ABC submitted a request for equitable adjustment (REA) to the buyer. In the REA, ABC requested $1,369,377.47 , which represented the difference in price between the parts called for by the original delivery order and the parts ABC ultimately delivered. The buyer rejected the request.
Question:
Which factor contributed most to the risk assumed by the contractor for this contract?
ABC Corporation (ABC) entered into a firm-fixed-price, indefinite-delivery/indefinite-quantity (IDIQ) contract with a Federal buyer for the purchase of various "Soviet-style" parts. The contract language allowed for changes to:
o Drawings, designs, or specifications when the supplies to be furnished are to be specially manufactured for the buyer; o The method of shipment or packing; and o Place of delivery.
The contract also specified that:
If any such change causes an increase or decrease in the cost of, or the time required for, performance of any part of the work under this contract, whether or not changed by the order, the buyer shall make an equitable adjustment in the contract price, the delivery schedule, or both, and shall modify the contract.
ABC was unable to obtain a particular part required to fulfill a delivery order under the contract, and missed the deadline for delivery. Two years after the deadline passed, with no delivery, the failure provided cause for termination for default under the conditions outlined in the contract. To avoid default, ABC entered into Bilateral Modification 4 with the buyer. The modification required ABC to provide additional parts as consideration for late delivery. The modification also stated that a new delivery date for the original delivery would be determined in another modification.
ABC remained unable to purchase the parts to fulfill the original order. A new modification, Bilateral Modification 7 , provided that ABC would deliver "new production" models of the parts in question, rather than the "new surplus" parts specified in the original delivery order. The idea to deliver new production models of the parts had originated with ABC and was accepted by the buyer. ABC did not attempt to negotiate any changes in price, no discussions of price were held, and no price adjustment was included in this modification.
ABC completed delivery of these parts on time. However, the new production models cost significantly more than the new surplus parts originally ordered.
Approximately four months later, ABC submitted a request for equitable adjustment (REA) to the buyer. In the REA, ABC requested $1,369,377.47 , which represented the difference in price between the parts called for by the original delivery order and the parts ABC ultimately delivered. The buyer rejected the request.
Question:
Which factor contributed most to the risk assumed by the contractor for this contract?
Correct Answer: B
Vote an answer
Explanation: Only visible for EduDump members. You can sign-up / login (it's free).
What is the key enabler to obtaining successful outcomes that are often measured by metrics of schedule timelines, cost effectiveness, quality standards, earned value, and other parameters that can quantify desired project results?
Correct Answer: D
Vote an answer
Explanation: Only visible for EduDump members. You can sign-up / login (it's free).
Decisions about which items to stock in each location and how much stock to keep on hand at various levels of operation are part of __________.
Correct Answer: A
Vote an answer
Explanation: Only visible for EduDump members. You can sign-up / login (it's free).
Contract management means the actions of a contract manager to _________.
Correct Answer: B
Vote an answer
Explanation: Only visible for EduDump members. You can sign-up / login (it's free).
Which of the following refers to a method for measuring project performance that compares the amount of work that was planned with what was actually accomplished to determine if cost and schedule performance went as planned?
Correct Answer: A
Vote an answer
Explanation: Only visible for EduDump members. You can sign-up / login (it's free).
__________ damages are awarded to the plaintiff when the defendant is guilty of fraud, malice, or oppression.
Correct Answer: D
Vote an answer
Explanation: Only visible for EduDump members. You can sign-up / login (it's free).
The Uniform Commercial Code applies to __________.
Correct Answer: B
Vote an answer
Explanation: Only visible for EduDump members. You can sign-up / login (it's free).
A proprietary information agreement (PIA) would be used __________.
Correct Answer: D
Vote an answer
Explanation: Only visible for EduDump members. You can sign-up / login (it's free).
Scenario 6.0: 2
ABC Corporation (ABC) entered into a firm-fixed-price, indefinite-delivery/indefinite-quantity (IDIQ) contract with a Federal buyer for the purchase of various "Soviet-style" parts. The contract language allowed for changes to:
o Drawings, designs, or specifications when the supplies to be furnished are to be specially manufactured for the buyer; o The method of shipment or packing; and o Place of delivery.
The contract also specified that:
If any such change causes an increase or decrease in the cost of, or the time required for, performance of any part of the work under this contract, whether or not changed by the order, the buyer shall make an equitable adjustment in the contract price, the delivery schedule, or both, and shall modify the contract.
ABC was unable to obtain a particular part required to fulfill a delivery order under the contract, and missed the deadline for delivery. Two years after the deadline passed, with no delivery, the failure provided cause for termination for default under the conditions outlined in the contract. To avoid default, ABC entered into Bilateral Modification 4 with the buyer. The modification required ABC to provide additional parts as consideration for late delivery. The modification also stated that a new delivery date for the original delivery would be determined in another modification.
ABC remained unable to purchase the parts to fulfill the original order. A new modification, Bilateral Modification 7 , provided that ABC would deliver "new production" models of the parts in question, rather than the "new surplus" parts specified in the original delivery order. The idea to deliver new production models of the parts had originated with ABC and was accepted by the buyer. ABC did not attempt to negotiate any changes in price, no discussions of price were held, and no price adjustment was included in this modification.
ABC completed delivery of these parts on time. However, the new production models cost significantly more than the new surplus parts originally ordered.
Approximately four months later, ABC submitted a request for equitable adjustment (REA) to the buyer. In the REA, ABC requested $1,369,377.47 , which represented the difference in price between the parts called for by the original delivery order and the parts ABC ultimately delivered. The buyer rejected the request.
Question:
The seller's difficulty executing this contract was due primarily to a failure in which of the following areas?
ABC Corporation (ABC) entered into a firm-fixed-price, indefinite-delivery/indefinite-quantity (IDIQ) contract with a Federal buyer for the purchase of various "Soviet-style" parts. The contract language allowed for changes to:
o Drawings, designs, or specifications when the supplies to be furnished are to be specially manufactured for the buyer; o The method of shipment or packing; and o Place of delivery.
The contract also specified that:
If any such change causes an increase or decrease in the cost of, or the time required for, performance of any part of the work under this contract, whether or not changed by the order, the buyer shall make an equitable adjustment in the contract price, the delivery schedule, or both, and shall modify the contract.
ABC was unable to obtain a particular part required to fulfill a delivery order under the contract, and missed the deadline for delivery. Two years after the deadline passed, with no delivery, the failure provided cause for termination for default under the conditions outlined in the contract. To avoid default, ABC entered into Bilateral Modification 4 with the buyer. The modification required ABC to provide additional parts as consideration for late delivery. The modification also stated that a new delivery date for the original delivery would be determined in another modification.
ABC remained unable to purchase the parts to fulfill the original order. A new modification, Bilateral Modification 7 , provided that ABC would deliver "new production" models of the parts in question, rather than the "new surplus" parts specified in the original delivery order. The idea to deliver new production models of the parts had originated with ABC and was accepted by the buyer. ABC did not attempt to negotiate any changes in price, no discussions of price were held, and no price adjustment was included in this modification.
ABC completed delivery of these parts on time. However, the new production models cost significantly more than the new surplus parts originally ordered.
Approximately four months later, ABC submitted a request for equitable adjustment (REA) to the buyer. In the REA, ABC requested $1,369,377.47 , which represented the difference in price between the parts called for by the original delivery order and the parts ABC ultimately delivered. The buyer rejected the request.
Question:
The seller's difficulty executing this contract was due primarily to a failure in which of the following areas?
Correct Answer: D
Vote an answer
Explanation: Only visible for EduDump members. You can sign-up / login (it's free).
Scenario 5.0: 1
Offeror C contested the exclusion of its proposal from the competitive range under a request for proposals (RFP) issued by the buyer for "aircraft logistics, integration, configuration management, and engineering" (ALICE) services. The seller would provide personnel to work at a buyer's location, and the buyer would direct all work and "establish work hours consistent with meeting the mission at each contract location." The RFP provided an estimated level of effort, and offerors completed a pricing model spreadsheet.
Proposals were to be evaluated on mission suitability, past performance, and cost/price. The mission suitability and past performance factors were approximately equal in importance, and each was more important than cost/price. The purpose of the mission suitability factor was to determine the offeror's ability to provide the required personnel at the required work hours to fulfill the contract need. It included several subfactors: management approach, overall management approach, staffing approach, and contract phase-in approach.
Offeror C argued that the buyer unfairly assessed a management approach weakness for failing to show a plan for complying with required work schedules and break times, failing to consider that the buyer establishes work hours consistent with mission needs, and failing to consider the buyer's intention to have night shift work on Sundays. Offeror C's proposal had discussed its approach to managing scheduling and breaks and stated that it would comply with collective bargaining agreement requirements. The buyer nevertheless judged the approach inadequate because it did not explain how Offeror C would enforce worker compliance, comparing the plan to a highway speed-limit sign that does not ensure motorists will not speed. GAO found that the RFP required offerors to explain their approaches to ensuring flexible scheduling and required breaks, but did not reasonably disclose that offerors also had to propose an enforcement mechanism.
Question:
The RFP required offerors to explain their approaches to ensuring that scheduling was flexible and provided required breaks. Was the buyer's assignment of a weakness to Offeror C's proposal reasonable?
Offeror C contested the exclusion of its proposal from the competitive range under a request for proposals (RFP) issued by the buyer for "aircraft logistics, integration, configuration management, and engineering" (ALICE) services. The seller would provide personnel to work at a buyer's location, and the buyer would direct all work and "establish work hours consistent with meeting the mission at each contract location." The RFP provided an estimated level of effort, and offerors completed a pricing model spreadsheet.
Proposals were to be evaluated on mission suitability, past performance, and cost/price. The mission suitability and past performance factors were approximately equal in importance, and each was more important than cost/price. The purpose of the mission suitability factor was to determine the offeror's ability to provide the required personnel at the required work hours to fulfill the contract need. It included several subfactors: management approach, overall management approach, staffing approach, and contract phase-in approach.
Offeror C argued that the buyer unfairly assessed a management approach weakness for failing to show a plan for complying with required work schedules and break times, failing to consider that the buyer establishes work hours consistent with mission needs, and failing to consider the buyer's intention to have night shift work on Sundays. Offeror C's proposal had discussed its approach to managing scheduling and breaks and stated that it would comply with collective bargaining agreement requirements. The buyer nevertheless judged the approach inadequate because it did not explain how Offeror C would enforce worker compliance, comparing the plan to a highway speed-limit sign that does not ensure motorists will not speed. GAO found that the RFP required offerors to explain their approaches to ensuring flexible scheduling and required breaks, but did not reasonably disclose that offerors also had to propose an enforcement mechanism.
Question:
The RFP required offerors to explain their approaches to ensuring that scheduling was flexible and provided required breaks. Was the buyer's assignment of a weakness to Offeror C's proposal reasonable?
Correct Answer: A
Vote an answer
Explanation: Only visible for EduDump members. You can sign-up / login (it's free).
In approaching negotiations, the buyer and seller should __________.
Correct Answer: A
Vote an answer
Explanation: Only visible for EduDump members. You can sign-up / login (it's free).
Upon receipt of owner-furnished property, the seller is responsible and accountable for the property as prescribed by the terms of the contract. This responsibility and accountability is called __________.
Correct Answer: B
Vote an answer
Explanation: Only visible for EduDump members. You can sign-up / login (it's free).