As part of the agreement with one of your suppliers, you must always order product by the 100s. For example, if the required supply is 105, you must order 200, if it's 275, you must order 300. Which item attributes will help you achieve this?
Correct Answer: D
Vote an answer
When planning for customer demand to be fulfilled from internal organizations or from a contract manufacturer, what are the four types of planned orders that can be generated? (Choose four.)
Correct Answer: A,B,C,E
Vote an answer
Explanation: Only visible for EduDump members. You can sign-up / login (it's free).
When analyzing demand fulfillment, what are the three types of recommendations that users can review and accept for expediting? (Choose three.)
Correct Answer: C,D,E
Vote an answer
Your customer wants to be able to manually change the input values in purchase orders and transfer orders for the suggested plan recommendations. Which two recommendations are released by supply chain planning to Oracle Supply Chain Orchestration Cloud? (Choose two.)
Correct Answer: A,B
Vote an answer
You are setting up the plan page layout for your customer.
In which of these requirements would you use an Infotile?
In which of these requirements would you use an Infotile?
Correct Answer: B
Vote an answer
Your client uses product categories and global sourcing rules for supply planning. However, their newest product doesn't follow these rules. For a specific item in the category, it needs to be sourced from a different supplier globally.
How should they set this up for the easiest maintenance, going forward?
How should they set this up for the easiest maintenance, going forward?
Correct Answer: D
Vote an answer
Which option outlines changes you can make to a simulation plan when evaluating demand and supply?
Correct Answer: C
Vote an answer
As a new planner, you want to test simulation set functionality. You have created a simulation set named
'Test Simulation Set.' In this simulation set, you have already added Item 98573. You would like to change the item specification 'Fixed Order Quantity' to 10 within this simulation set.
Which sequence will allow you to accomplish this task?
'Test Simulation Set.' In this simulation set, you have already added Item 98573. You would like to change the item specification 'Fixed Order Quantity' to 10 within this simulation set.
Which sequence will allow you to accomplish this task?
Correct Answer: A
Vote an answer
0
0
0
10