SAP C-TS422-1909 Actual Free Exam Questions & Community Discussion
In which data object is the production line (Repetitive manufacturing relevant work center) maintained?
Please choose the correct answer.
Response:
Please choose the correct answer.
Response:
Correct Answer: B
Vote an answer
The SAP Kanban procedure could be used to trigger which of the following kinds of replenishment?
There are 2 correct answers to this question.
Response:
There are 2 correct answers to this question.
Response:
Correct Answer: B,C
Vote an answer
Which technological advances enabled the development of SAP S/4HANA as the digital core?
There are 3 correct answers to this question.
Response:
There are 3 correct answers to this question.
Response:
Correct Answer: A,B,E
Vote an answer
At the end of the MRP run you receive the exception message "Reschedule In Operation". What caused the message to be generated?
Please choose the correct answer.
Response:
Please choose the correct answer.
Response:
Correct Answer: D
Vote an answer
How can you avoid order proposals for planned independent requirements with dates in the past?
There are 2 correct answers to this question.
Response:
There are 2 correct answers to this question.
Response:
Correct Answer: C,D
Vote an answer
The setup time on the production line to produce a material is extensive. You would like to avoid multiple setups and limit the production of the material based on a planning calendar.
Which type of lot size procedure should you use to accomplish this?
Please choose the correct answer.
Response:
Which type of lot size procedure should you use to accomplish this?
Please choose the correct answer.
Response:
Correct Answer: A
Vote an answer
Which material master setting is required to use the repetitive planning table for production with production orders?
Please choose the correct answer.
Response:
Please choose the correct answer.
Response:
Correct Answer: B
Vote an answer
Which data model changes have been implemented in Sales and Distribution?
There are 3 correct answers to this question.
Response:
There are 3 correct answers to this question.
Response:
Correct Answer: A,C,D
Vote an answer
Where can you maintain consumption mode and consumption periods for planning strategies?
There are 2 correct answers to this question.
Response:
There are 2 correct answers to this question.
Response:
Correct Answer: A,C
Vote an answer
Which reports can you access via the order and resource reporting transaction in advanced planning?
There are 3 correct answers to this question.
Response:
There are 3 correct answers to this question.
Response:
Correct Answer: C,D,E
Vote an answer