Which of the following conflict resolution techniques results in mutual agreement among conflicting parties?
Correct Answer: A Vote an answer
A project manager has inherited a project that is $5 million over budget. Which of the following would the project manager do to help determine the root cause of the budget overrun?
Correct Answer: D Vote an answer
A project is having issues because uncertain events have occurred that were not tracked and planned for. This could have been avoided by using:
Correct Answer: A Vote an answer
As a result of changes in the economy, it has been communicated that the current costs for needed components have doubled from what was originally budgeted. If the procurement occurs, this would result in exceeding the cost baseline for the project. Which of the following actions should the project manager take?
Correct Answer: B Vote an answer
Which of the following can aid in the identification of trends?
Correct Answer: C Vote an answer
A project manager of a particular project receives formal notification that a vendor has gone out of business. New vendors with similar products at similar costs have been identified. Which of the following should the project manager do FIRST?
Correct Answer: A Vote an answer
An individual's responsibilities for Project A include: 1) Select the project leader, 2) Assure objectives are in-line with strategic goals/directions of the organization, 3) Assure the needed resources are available for successful project completion. This individual's role is:
Correct Answer: A Vote an answer
A status report shows that the earned value is $50,000, the planned value is $40,000, and actual costs are $45,000. Which of the following is the SPI of the project, and is the project ahead or behind schedule?
Correct Answer: D Vote an answer
Which of the following is an acknowledgement that risks may occur, but a response is in place to minimize the risk impact?
Correct Answer: A Vote an answer
A project team is writing a new customized point of sale software. The software needs to calculate sales tax 100% of the time on all taxable items of a receipt. This requirement should be documented in which of the following?
Correct Answer: B Vote an answer
Which of the following can be identified using a run chart?
Correct Answer: A Vote an answer
Which of the following is the MAIN difference between bottom up and top down cost estimation?
Correct Answer: B Vote an answer
Which of the following risk responses would be characterized by having knowledge of a risk event and taking advantage of the risk?
Correct Answer: D Vote an answer
A project has two resources scheduled to work 40 hours a week for four weeks, both at $85.00 an hour. One resource called in sick for 16 hours, while the other resource worked four hours additional. Which of the following is the cost of the resources?
Correct Answer: D Vote an answer