What is NOT a cost component based on the Nokia cost management guideline?
Correct Answer: C
Vote an answer
What is the relationship between actual cost, EAC and ETC?
Correct Answer: B
Vote an answer
A project risk is a(n) __________ event or condition that, if it occurs, has a ___________ effect on at least one project objective:
Correct Answer: D
Vote an answer
The product line is unable to meet a software release committed timeline. Due to this delay, resources dedicated to the installation need to remain available for an additional month. Additionally, the project will be liable to pay penalties based on contract conditions. How should these extra costs be reported?
Correct Answer: C
Vote an answer
What is the duration of short term planning (STP) period?
Correct Answer: C
Vote an answer
Your project is ongoing, all partner contracts have been renegotiated and new, higher prices came into effect immediately. If all the other circumstances in your project remain unchanged, your CPI value will:
Correct Answer: C
Vote an answer
Decomposing the major deliverables into smaller, more manageable components to provide better control is called:
Correct Answer: A
Vote an answer
The estimated value of the work actually accomplished is:
Correct Answer: C
Vote an answer
Which of the following statements is not in line with reporting rules? New non-planned Risk identified with a significant value:
Correct Answer: C
Vote an answer